NYC DEP

Industry:

Plant Maintenance

Client:

NYC DEP

Location:

Port Richmond, NY

General Contractor:

Wittman Plumbing

Engineers:

In 2006 Walker Diving was asked to replace a 36” gate and actuator in an effluent channel at the Port Richmond Waste Treatment Plant for the New York City DEP. Walker first had to take measurements and then handle the ordering of a Fontaine gate. Installation involved several steps including core drilling as well anchoring the gate to the wall. This involved working quickly during the night time when the flow was reduced to a minimum.

WALKER DIVING UNDERWATER CONSTRUCTION LLC


75 Waterford Road,

Hammonton, NJ 08037

Phone: 609-704-8650

Emergency Contact: 609-992-3796

Email: info@walkerdiving.com